Gazprom Neft has chosen Tecnicas Reunidas S.A. (Spain) to manage the construction of the delayed coking unuit (DCU) at its Moscow Refinery’s future deep refining complex. Tecnicas Reunidas S.A. specialists will be responsible for managing project design and equipment deliveries (including deliveries of Russian-manufactured equipment), as well as managing and overseeing construction and installation works and acceptance testing. The contract is worth more than ₽20 billion. Works are expected to be complete by 2025.
Tecnicas Reunidas S.A. has extensive experience in developing high-tech production facilities — the company’s engineers having successfully implemented a range of projects in Australia, Canada, Great Britain, Norway and the United States of America. Stringent adherence to environmental standards and requirements will be front of mind in all works at the Moscow Refinery.